Customer Project


Project Start Date: Fri 15/03/02
Project Finish Date: Fri 23/08/02

Tasks

ID
Task Name
DurationStartFinishResource Names% Complete
1
Submit proposal
0 daysFri 15/03/02Fri 15/03/02Management0%
2
Decision on preferred bidders
0 daysMon 18/03/02Mon 18/03/02The Society of C & P0%
3
Present propsal
0 daysFri 29/03/02Fri 29/03/02Management0%
4
Award contract
0 daysFri 29/03/02Fri 29/03/02The Society of C & P0%
5
Scope
4 daysMon 01/04/02Thu 04/04/02 0%
6
Confirm project scope
8 hrsMon 01/04/02Mon 01/04/02Management0%
7
Define preliminary resources
1 dayTue 02/04/02Tue 02/04/02Project Manager0%
8
Secure initial resources
2 daysWed 03/04/02Thu 04/04/02Project Manager0%
9
Scope complete
0 daysThu 04/04/02Thu 04/04/02 0%
10
Analysis/Software Requirements
14.5 daysFri 05/04/02Thu 25/04/02 0%
11
Review needs analysis
2 daysFri 05/04/02Mon 08/04/02Management0%
12
Draft preliminary software specifications
6 daysTue 09/04/02Tue 16/04/02Analyst0%
13
Confirm preliminary budget
2 daysWed 17/04/02Thu 18/04/02Project Manager0%
14
Review software specifications/budget with team
4 hrsFri 19/04/02Fri 19/04/02Project Manager,Analyst0%
15
Incorporate feedback on software specifications
1 dayFri 19/04/02Mon 22/04/02Analyst0%
16
Develop delivery timeline
1 dayMon 22/04/02Tue 23/04/02Project Manager0%
17
Obtain approvals to proceed (concept, timeline, budget)
1 dayTue 23/04/02Wed 24/04/02Management,Project Manager0%
18
Secure required resources
1 dayWed 24/04/02Thu 25/04/02Project Manager0%
19
Analysis complete
0 daysThu 25/04/02Thu 25/04/02 0%
20
Design
17.5 daysThu 25/04/02Mon 20/05/02 0%
21
Review preliminary software specifications & graphical design
3 daysThu 25/04/02Tue 30/04/02Analyst0%
22
Develop functional specifications
7 daysTue 30/04/02Thu 09/05/02Analyst0%
23
Develop prototype based on functional specifications
4 daysThu 09/05/02Wed 15/05/02Analyst0%
24
Review functional specifications
2 daysWed 15/05/02Fri 17/05/02Management0%
25
Incorporate feedback into functional specifications
1 dayFri 17/05/02Mon 20/05/02Management0%
26
Obtain approval to proceed
4 hrsMon 20/05/02Mon 20/05/02Management,Project Manager0%
27
Design complete
0 daysMon 20/05/02Mon 20/05/02 0%
28
Development
38 daysTue 21/05/02Thu 11/07/02 0%
29
Review functional specifications
1 dayTue 21/05/02Tue 21/05/02Developer0%
30
Identify modular/tiered design parameters
1 dayWed 22/05/02Wed 22/05/02Developer0%
31
Assign development staff
1 dayThu 23/05/02Thu 23/05/02Developer0%
32
Develop code
35 daysFri 24/05/02Thu 11/07/02Developer0%
33
Developer testing (primary debugging)
15 daysWed 05/06/02Wed 26/06/02Developer0%
34
Development complete
0 daysWed 26/06/02Wed 26/06/02 0%
35
Testing
53.75 daysTue 21/05/02Fri 02/08/02 0%
36
Develop unit test plans using product specifications
4 daysTue 21/05/02Fri 24/05/02Testers0%
37
Develop integration test plans using product specifications
4 daysTue 21/05/02Fri 24/05/02Testers0%
38
Unit Testing
15 daysWed 26/06/02Wed 17/07/02 0%
39
Review modular code
5 daysWed 26/06/02Wed 03/07/02Testers0%
40
Test component modules to product specifications
2 daysWed 03/07/02Fri 05/07/02Testers0%
41
Identify anomalies to product specifications
3 daysFri 05/07/02Wed 10/07/02Testers0%
42
Modify code
3 daysWed 10/07/02Mon 15/07/02Testers0%
43
Re-test modified code
2 daysMon 15/07/02Wed 17/07/02Testers0%
44
Unit testing complete
0 daysWed 17/07/02Wed 17/07/02 0%
45
Integration Testing
12 daysWed 17/07/02Fri 02/08/02 0%
46
Test module integration
5 daysWed 17/07/02Wed 24/07/02Testers0%
47
Identify anomalies to specifications
2 daysWed 24/07/02Fri 26/07/02Testers0%
48
Modify code
3 daysFri 26/07/02Wed 31/07/02Testers0%
49
Re-test modified code
2 daysWed 31/07/02Fri 02/08/02Testers0%
50
Integration testing complete
0 daysFri 02/08/02Fri 02/08/02 0%
51
Training
50.75 daysTue 21/05/02Tue 30/07/02 0%
52
Develop training specifications for end users
3 daysTue 21/05/02Thu 23/05/02Trainers0%
53
Develop training specifications for helpdesk support staff
3 daysTue 21/05/02Thu 23/05/02Trainers0%
54
Identify training delivery methodology (computer based training, classroom, etc.)
2 daysTue 21/05/02Wed 22/05/02Trainers0%
55
Develop training materials
3 wksWed 26/06/02Wed 17/07/02Trainers0%
56
Conduct training usability study
4 daysWed 17/07/02Tue 23/07/02Trainers0%
57
Finalize training materials
3 daysTue 23/07/02Fri 26/07/02Trainers0%
58
Develop training delivery mechanism
2 daysFri 26/07/02Tue 30/07/02Trainers0%
59
Training materials complete
0 daysTue 30/07/02Tue 30/07/02 0%
60
Documentation
40.5 daysTue 21/05/02Tue 16/07/02 0%
61
Develop Help specification
1 dayTue 21/05/02Tue 21/05/02Technical Communicators0%
62
Develop Help system
3 wksTue 18/06/02Tue 09/07/02Technical Communicators0%
63
Review Help documentation
3 daysTue 09/07/02Fri 12/07/02Technical Communicators0%
64
Incorporate Help documentation feedback
2 daysFri 12/07/02Tue 16/07/02Technical Communicators0%
65
Develop user manuals specifications
2 daysTue 21/05/02Wed 22/05/02Technical Communicators0%
66
Develop user manuals
3 wksTue 18/06/02Tue 09/07/02Technical Communicators0%
67
Review all user documentation
2 daysTue 09/07/02Thu 11/07/02Technical Communicators0%
68
Incorporate user documentation feedback
2 daysThu 11/07/02Mon 15/07/02Technical Communicators0%
69
Documentation complete
0 daysTue 16/07/02Tue 16/07/02 0%
70
Pilot
78.25 daysThu 25/04/02Tue 13/08/02 0%
71
Identify test group
1 dayThu 25/04/02Fri 26/04/02Project Manager0%
72
Develop software delivery mechanism
1 dayFri 26/04/02Mon 29/04/02 0%
73
Install/deploy software
1 dayFri 02/08/02Mon 05/08/02Deployment Team0%
74
Obtain user feedback
1 wkMon 05/08/02Mon 12/08/02Deployment Team0%
75
Evaluate testing information
1 dayMon 12/08/02Tue 13/08/02Deployment Team0%
76
Pilot complete
0 daysTue 13/08/02Tue 13/08/02 0%
77
Deployment
5 daysTue 13/08/02Tue 20/08/02 0%
78
Determine final deployment strategy
1 dayTue 13/08/02Wed 14/08/02Deployment Team0%
79
Develop deployment methodology
1 dayWed 14/08/02Thu 15/08/02Deployment Team0%
80
Secure deployment resources
1 dayThu 15/08/02Fri 16/08/02Deployment Team0%
81
Train support staff
1 dayFri 16/08/02Mon 19/08/02Deployment Team0%
82
Deploy software
1 dayMon 19/08/02Tue 20/08/02Deployment Team0%
83
Deployment complete
0 daysTue 20/08/02Tue 20/08/02 0%
84
Post Implementation Review
3 daysTue 20/08/02Fri 23/08/02 0%
85
Document lessons learned
1 dayTue 20/08/02Wed 21/08/02Project Manager0%
86
Distribute to team members
1 dayWed 21/08/02Thu 22/08/02Project Manager0%
87
Create software maintenance team
1 dayThu 22/08/02Fri 23/08/02Project Manager0%
88
Post implementation review complete
0 daysFri 23/08/02Fri 23/08/02 0%
89
Software development template complete
0 daysFri 23/08/02Fri 23/08/02 0%

Resources

IDNameGroupMax UnitsPeak Units
1Management 100%100%
2Project Manager 100%100%
3Creative Director 100%0%
4Analyst 100%100%
5Developer 100%200%
6Testers 100%200%
7Trainers 100%300%
8Technical Communicators 100%200%
9Deployment Team 100%100%
10The Society of C & P 100%0%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete
1Submit proposal Management0 hrsFri 15/03/02Fri 15/03/020%
2Decision on preferred biddersThe Society of C & P0 hrsMon 18/03/02Mon 18/03/020%
3Present propsalManagement0 hrsFri 29/03/02Fri 29/03/020%
4Award contractThe Society of C & P0 hrsFri 29/03/02Fri 29/03/020%
6Confirm project scopeManagement8 hrsMon 01/04/02Mon 01/04/020%
7Define preliminary resourcesProject Manager8 hrsTue 02/04/02Tue 02/04/020%
8Secure initial resourcesProject Manager16 hrsWed 03/04/02Thu 04/04/020%
11Review needs analysisManagement16 hrsFri 05/04/02Mon 08/04/020%
12Draft preliminary software specificationsAnalyst48 hrsTue 09/04/02Tue 16/04/020%
13Confirm preliminary budgetProject Manager16 hrsWed 17/04/02Thu 18/04/020%
14Review software specifications/budget with teamProject Manager4 hrsFri 19/04/02Fri 19/04/020%
14Review software specifications/budget with teamAnalyst4 hrsFri 19/04/02Fri 19/04/020%
15Incorporate feedback on software specificationsAnalyst8 hrsFri 19/04/02Mon 22/04/020%
16Develop delivery timelineProject Manager8 hrsMon 22/04/02Tue 23/04/020%
17Obtain approvals to proceed (concept, timeline, budget)Management8 hrsTue 23/04/02Wed 24/04/020%
17Obtain approvals to proceed (concept, timeline, budget)Project Manager8 hrsTue 23/04/02Wed 24/04/020%
18Secure required resourcesProject Manager8 hrsWed 24/04/02Thu 25/04/020%
21Review preliminary software specifications & graphical designAnalyst24 hrsThu 25/04/02Tue 30/04/020%
22Develop functional specificationsAnalyst56 hrsTue 30/04/02Thu 09/05/020%
23Develop prototype based on functional specificationsAnalyst32 hrsThu 09/05/02Wed 15/05/020%
24Review functional specificationsManagement16 hrsWed 15/05/02Fri 17/05/020%
25Incorporate feedback into functional specificationsManagement8 hrsFri 17/05/02Mon 20/05/020%
26Obtain approval to proceedManagement4 hrsMon 20/05/02Mon 20/05/020%
26Obtain approval to proceedProject Manager4 hrsMon 20/05/02Mon 20/05/020%
29Review functional specificationsDeveloper8 hrsTue 21/05/02Tue 21/05/020%
30Identify modular/tiered design parametersDeveloper8 hrsWed 22/05/02Wed 22/05/020%
31Assign development staffDeveloper8 hrsThu 23/05/02Thu 23/05/020%
32Develop codeDeveloper280 hrsFri 24/05/02Thu 11/07/020%
33Developer testing (primary debugging)Developer120 hrsWed 05/06/02Wed 26/06/020%
36Develop unit test plans using product specificationsTesters32 hrsTue 21/05/02Fri 24/05/020%
37Develop integration test plans using product specificationsTesters32 hrsTue 21/05/02Fri 24/05/020%
39Review modular codeTesters40 hrsWed 26/06/02Wed 03/07/020%
40Test component modules to product specificationsTesters16 hrsWed 03/07/02Fri 05/07/020%
41Identify anomalies to product specificationsTesters24 hrsFri 05/07/02Wed 10/07/020%
42Modify codeTesters24 hrsWed 10/07/02Mon 15/07/020%
43Re-test modified codeTesters16 hrsMon 15/07/02Wed 17/07/020%
46Test module integrationTesters40 hrsWed 17/07/02Wed 24/07/020%
47Identify anomalies to specificationsTesters16 hrsWed 24/07/02Fri 26/07/020%
48Modify codeTesters24 hrsFri 26/07/02Wed 31/07/020%
49Re-test modified codeTesters16 hrsWed 31/07/02Fri 02/08/020%
52Develop training specifications for end usersTrainers24 hrsTue 21/05/02Thu 23/05/020%
53Develop training specifications for helpdesk support staffTrainers24 hrsTue 21/05/02Thu 23/05/020%
54Identify training delivery methodology (computer based training, classroom, etc.)Trainers16 hrsTue 21/05/02Wed 22/05/020%
55Develop training materialsTrainers120 hrsWed 26/06/02Wed 17/07/020%
56Conduct training usability studyTrainers32 hrsWed 17/07/02Tue 23/07/020%
57Finalize training materialsTrainers24 hrsTue 23/07/02Fri 26/07/020%
58Develop training delivery mechanismTrainers16 hrsFri 26/07/02Tue 30/07/020%
61Develop Help specificationTechnical Communicators8 hrsTue 21/05/02Tue 21/05/020%
62Develop Help systemTechnical Communicators120 hrsTue 18/06/02Tue 09/07/020%
63Review Help documentationTechnical Communicators24 hrsTue 09/07/02Fri 12/07/020%
64Incorporate Help documentation feedbackTechnical Communicators16 hrsFri 12/07/02Tue 16/07/020%
65Develop user manuals specificationsTechnical Communicators16 hrsTue 21/05/02Wed 22/05/020%
66Develop user manualsTechnical Communicators120 hrsTue 18/06/02Tue 09/07/020%
67Review all user documentationTechnical Communicators16 hrsTue 09/07/02Thu 11/07/020%
68Incorporate user documentation feedbackTechnical Communicators16 hrsThu 11/07/02Mon 15/07/020%
71Identify test groupProject Manager8 hrsThu 25/04/02Fri 26/04/020%
73Install/deploy softwareDeployment Team8 hrsFri 02/08/02Mon 05/08/020%
74Obtain user feedbackDeployment Team40 hrsMon 05/08/02Mon 12/08/020%
75Evaluate testing informationDeployment Team8 hrsMon 12/08/02Tue 13/08/020%
78Determine final deployment strategyDeployment Team8 hrsTue 13/08/02Wed 14/08/020%
79Develop deployment methodologyDeployment Team8 hrsWed 14/08/02Thu 15/08/020%
80Secure deployment resourcesDeployment Team8 hrsThu 15/08/02Fri 16/08/020%
81Train support staffDeployment Team8 hrsFri 16/08/02Mon 19/08/020%
82Deploy softwareDeployment Team8 hrsMon 19/08/02Tue 20/08/020%
85Document lessons learnedProject Manager8 hrsTue 20/08/02Wed 21/08/020%
86Distribute to team membersProject Manager8 hrsWed 21/08/02Thu 22/08/020%
87Create software maintenance teamProject Manager8 hrsThu 22/08/02Fri 23/08/020%