Customer Project


Project Start Date: Fri 15/03/02
Project Finish Date: Fri 23/08/02

Task Data

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
Submit proposal
0 daysFri 15/03/02Fri 15/03/02 Management
2
Decision on preferred bidders
0 daysMon 18/03/02Mon 18/03/02 The Society of C & P
3
Present propsal
0 daysFri 29/03/02Fri 29/03/022Management
4
Award contract
0 daysFri 29/03/02Fri 29/03/023The Society of C & P
5
Scope
4 daysMon 01/04/02Thu 04/04/024 
6
Confirm project scope
8 hrsMon 01/04/02Mon 01/04/02 Management
7
Define preliminary resources
1 dayTue 02/04/02Tue 02/04/026Project Manager
8
Secure initial resources
2 daysWed 03/04/02Thu 04/04/027Project Manager
9
Scope complete
0 daysThu 04/04/02Thu 04/04/028 
10
Analysis/Software Requirements
14.5 daysFri 05/04/02Thu 25/04/02  
11
Review needs analysis
2 daysFri 05/04/02Mon 08/04/029Management
12
Draft preliminary software specifications
6 daysTue 09/04/02Tue 16/04/0211Analyst
13
Confirm preliminary budget
2 daysWed 17/04/02Thu 18/04/0212Project Manager
14
Review software specifications/budget with team
4 hrsFri 19/04/02Fri 19/04/0213Project Manager,Analyst
15
Incorporate feedback on software specifications
1 dayFri 19/04/02Mon 22/04/0214Analyst
16
Develop delivery timeline
1 dayMon 22/04/02Tue 23/04/0215Project Manager
17
Obtain approvals to proceed (concept, timeline, budget)
1 dayTue 23/04/02Wed 24/04/0216Management,Project Manager
18
Secure required resources
1 dayWed 24/04/02Thu 25/04/0217Project Manager
19
Analysis complete
0 daysThu 25/04/02Thu 25/04/0218 
20
Design
17.5 daysThu 25/04/02Mon 20/05/02  
21
Review preliminary software specifications & graphical design
3 daysThu 25/04/02Tue 30/04/0219Analyst
22
Develop functional specifications
7 daysTue 30/04/02Thu 09/05/0221Analyst
23
Develop prototype based on functional specifications
4 daysThu 09/05/02Wed 15/05/0222Analyst
24
Review functional specifications
2 daysWed 15/05/02Fri 17/05/0223Management
25
Incorporate feedback into functional specifications
1 dayFri 17/05/02Mon 20/05/0224Management
26
Obtain approval to proceed
4 hrsMon 20/05/02Mon 20/05/0225Management,Project Manager
27
Design complete
0 daysMon 20/05/02Mon 20/05/0226 
28
Development
38 daysTue 21/05/02Thu 11/07/02  
29
Review functional specifications
1 dayTue 21/05/02Tue 21/05/0227Developer
30
Identify modular/tiered design parameters
1 dayWed 22/05/02Wed 22/05/0229Developer
31
Assign development staff
1 dayThu 23/05/02Thu 23/05/0230Developer
32
Develop code
35 daysFri 24/05/02Thu 11/07/0231Developer
33
Developer testing (primary debugging)
15 daysWed 05/06/02Wed 26/06/0232FS-75%Developer
34
Development complete
0 daysWed 26/06/02Wed 26/06/0233 
35
Testing
53.75 daysTue 21/05/02Fri 02/08/02  
36
Develop unit test plans using product specifications
4 daysTue 21/05/02Fri 24/05/0227Testers
37
Develop integration test plans using product specifications
4 daysTue 21/05/02Fri 24/05/0227Testers
38
Unit Testing
15 daysWed 26/06/02Wed 17/07/02  
39
Review modular code
5 daysWed 26/06/02Wed 03/07/0236,34Testers
40
Test component modules to product specifications
2 daysWed 03/07/02Fri 05/07/0234,39Testers
41
Identify anomalies to product specifications
3 daysFri 05/07/02Wed 10/07/0240Testers
42
Modify code
3 daysWed 10/07/02Mon 15/07/0241Testers
43
Re-test modified code
2 daysMon 15/07/02Wed 17/07/0242Testers
44
Unit testing complete
0 daysWed 17/07/02Wed 17/07/0243 
45
Integration Testing
12 daysWed 17/07/02Fri 02/08/02  
46
Test module integration
5 daysWed 17/07/02Wed 24/07/0244Testers
47
Identify anomalies to specifications
2 daysWed 24/07/02Fri 26/07/0246Testers
48
Modify code
3 daysFri 26/07/02Wed 31/07/0247Testers
49
Re-test modified code
2 daysWed 31/07/02Fri 02/08/0248Testers
50
Integration testing complete
0 daysFri 02/08/02Fri 02/08/0249 
51
Training
50.75 daysTue 21/05/02Tue 30/07/02  
52
Develop training specifications for end users
3 daysTue 21/05/02Thu 23/05/0227Trainers
53
Develop training specifications for helpdesk support staff
3 daysTue 21/05/02Thu 23/05/0227Trainers
54
Identify training delivery methodology (computer based training, classroom, etc.)
2 daysTue 21/05/02Wed 22/05/0227Trainers
55
Develop training materials
3 wksWed 26/06/02Wed 17/07/0252,34,53,54Trainers
56
Conduct training usability study
4 daysWed 17/07/02Tue 23/07/0255Trainers
57
Finalize training materials
3 daysTue 23/07/02Fri 26/07/0256Trainers
58
Develop training delivery mechanism
2 daysFri 26/07/02Tue 30/07/0257Trainers
59
Training materials complete
0 daysTue 30/07/02Tue 30/07/0258 
60
Documentation
40.5 daysTue 21/05/02Tue 16/07/02  
61
Develop Help specification
1 dayTue 21/05/02Tue 21/05/0227Technical Communicators
62
Develop Help system
3 wksTue 18/06/02Tue 09/07/0261,32FS-50%Technical Communicators
63
Review Help documentation
3 daysTue 09/07/02Fri 12/07/0262Technical Communicators
64
Incorporate Help documentation feedback
2 daysFri 12/07/02Tue 16/07/0263Technical Communicators
65
Develop user manuals specifications
2 daysTue 21/05/02Wed 22/05/0227Technical Communicators
66
Develop user manuals
3 wksTue 18/06/02Tue 09/07/0265,32FS-50%Technical Communicators
67
Review all user documentation
2 daysTue 09/07/02Thu 11/07/0266Technical Communicators
68
Incorporate user documentation feedback
2 daysThu 11/07/02Mon 15/07/0267Technical Communicators
69
Documentation complete
0 daysTue 16/07/02Tue 16/07/0268,64 
70
Pilot
78.25 daysThu 25/04/02Tue 13/08/02  
71
Identify test group
1 dayThu 25/04/02Fri 26/04/0219Project Manager
72
Develop software delivery mechanism
1 dayFri 26/04/02Mon 29/04/0271 
73
Install/deploy software
1 dayFri 02/08/02Mon 05/08/0250,72,69,59Deployment Team
74
Obtain user feedback
1 wkMon 05/08/02Mon 12/08/0273Deployment Team
75
Evaluate testing information
1 dayMon 12/08/02Tue 13/08/0274Deployment Team
76
Pilot complete
0 daysTue 13/08/02Tue 13/08/0275 
77
Deployment
5 daysTue 13/08/02Tue 20/08/02  
78
Determine final deployment strategy
1 dayTue 13/08/02Wed 14/08/0276Deployment Team
79
Develop deployment methodology
1 dayWed 14/08/02Thu 15/08/0278Deployment Team
80
Secure deployment resources
1 dayThu 15/08/02Fri 16/08/0279Deployment Team
81
Train support staff
1 dayFri 16/08/02Mon 19/08/0280Deployment Team
82
Deploy software
1 dayMon 19/08/02Tue 20/08/0281Deployment Team
83
Deployment complete
0 daysTue 20/08/02Tue 20/08/0282 
84
Post Implementation Review
3 daysTue 20/08/02Fri 23/08/02  
85
Document lessons learned
1 dayTue 20/08/02Wed 21/08/0283Project Manager
86
Distribute to team members
1 dayWed 21/08/02Thu 22/08/0285Project Manager
87
Create software maintenance team
1 dayThu 22/08/02Fri 23/08/0286Project Manager
88
Post implementation review complete
0 daysFri 23/08/02Fri 23/08/0287 
89
Software development template complete
0 daysFri 23/08/02Fri 23/08/0288