Customer Project


Project Start Date: Fri 15/03/02
Project Finish Date: Fri 23/08/02

Top Level Tasks

ID
Task Name
DurationStartFinish% CompleteCostWork
1
Submit proposal
0 daysFri 15/03/02Fri 15/03/020%£0.000 hrs
2
Decision on preferred bidders
0 daysMon 18/03/02Mon 18/03/020%£0.000 hrs
3
Present propsal
0 daysFri 29/03/02Fri 29/03/020%£0.000 hrs
4
Award contract
0 daysFri 29/03/02Fri 29/03/020%£0.000 hrs
5
Scope
4 daysMon 01/04/02Thu 04/04/020%£1,480.0032 hrs
10
Analysis/Software Requirements
14.5 daysFri 05/04/02Thu 25/04/020%£5,280.00128 hrs
20
Design
17.5 daysThu 25/04/02Mon 20/05/020%£5,500.00144 hrs
28
Development
38 daysTue 21/05/02Thu 11/07/020%£8,480.00424 hrs
35
Testing
53.75 daysTue 21/05/02Fri 02/08/020%£5,600.00280 hrs
51
Training
50.75 daysTue 21/05/02Tue 30/07/020%£8,960.00256 hrs
60
Documentation
40.5 daysTue 21/05/02Tue 16/07/020%£11,760.00336 hrs
70
Pilot
78.25 daysThu 25/04/02Tue 13/08/020%£2,320.0064 hrs
77
Deployment
5 daysTue 13/08/02Tue 20/08/020%£1,400.0040 hrs
84
Post Implementation Review
3 daysTue 20/08/02Fri 23/08/020%£1,080.0024 hrs
89
Software development template complete
0 daysFri 23/08/02Fri 23/08/020%£0.000 hrs