| ID | Task Name | Duration | Start | Finish | % Complete | Cost | Work |
| 1 | Submit proposal | 0 days | Fri 15/03/02 | Fri 15/03/02 | 0% | £0.00 | 0 hrs |
| 2 | Decision on preferred bidders | 0 days | Mon 18/03/02 | Mon 18/03/02 | 0% | £0.00 | 0 hrs |
| 3 | Present propsal | 0 days | Fri 29/03/02 | Fri 29/03/02 | 0% | £0.00 | 0 hrs |
| 4 | Award contract | 0 days | Fri 29/03/02 | Fri 29/03/02 | 0% | £0.00 | 0 hrs |
| 5 | Scope | 4 days | Mon 01/04/02 | Thu 04/04/02 | 0% | £1,480.00 | 32 hrs |
| 10 | Analysis/Software Requirements | 14.5 days | Fri 05/04/02 | Thu 25/04/02 | 0% | £5,280.00 | 128 hrs |
| 20 | Design | 17.5 days | Thu 25/04/02 | Mon 20/05/02 | 0% | £5,500.00 | 144 hrs |
| 28 | Development | 38 days | Tue 21/05/02 | Thu 11/07/02 | 0% | £8,480.00 | 424 hrs |
| 35 | Testing | 53.75 days | Tue 21/05/02 | Fri 02/08/02 | 0% | £5,600.00 | 280 hrs |
| 51 | Training | 50.75 days | Tue 21/05/02 | Tue 30/07/02 | 0% | £8,960.00 | 256 hrs |
| 60 | Documentation | 40.5 days | Tue 21/05/02 | Tue 16/07/02 | 0% | £11,760.00 | 336 hrs |
| 70 | Pilot | 78.25 days | Thu 25/04/02 | Tue 13/08/02 | 0% | £2,320.00 | 64 hrs |
| 77 | Deployment | 5 days | Tue 13/08/02 | Tue 20/08/02 | 0% | £1,400.00 | 40 hrs |
| 84 | Post Implementation Review | 3 days | Tue 20/08/02 | Fri 23/08/02 | 0% | £1,080.00 | 24 hrs |
| 89 | Software development template complete | 0 days | Fri 23/08/02 | Fri 23/08/02 | 0% | £0.00 | 0 hrs |
|