Customer Project


Project Start Date: Fri 15/03/02
Project Finish Date: Fri 23/08/02

Who Does What

Resources and Assignments
Start Finish Work
Unassigned
Thu 04/04/02 Fri 23/08/02 0 hrs
Scope complete
Thu 04/04/02 Thu 04/04/02 0 hrs
Analysis complete
Thu 25/04/02 Thu 25/04/02 0 hrs
Design complete
Mon 20/05/02 Mon 20/05/02 0 hrs
Development complete
Wed 26/06/02 Wed 26/06/02 0 hrs
Unit testing complete
Wed 17/07/02 Wed 17/07/02 0 hrs
Integration testing complete
Fri 02/08/02 Fri 02/08/02 0 hrs
Training materials complete
Tue 30/07/02 Tue 30/07/02 0 hrs
Documentation complete
Tue 16/07/02 Tue 16/07/02 0 hrs
Develop software delivery mechanism
Fri 26/04/02 Mon 29/04/02 0 hrs
Pilot complete
Tue 13/08/02 Tue 13/08/02 0 hrs
Deployment complete
Tue 20/08/02 Tue 20/08/02 0 hrs
Post implementation review complete
Fri 23/08/02 Fri 23/08/02 0 hrs
Software development template complete
Fri 23/08/02 Fri 23/08/02 0 hrs
Management
Fri 15/03/02 Mon 20/05/02 60 hrs
Submit proposal
Fri 15/03/02 Fri 15/03/02 0 hrs
Present propsal
Fri 29/03/02 Fri 29/03/02 0 hrs
Confirm project scope
Mon 01/04/02 Mon 01/04/02 8 hrs
Review needs analysis
Fri 05/04/02 Mon 08/04/02 16 hrs
Obtain approvals to proceed (concept, timeline, budget)
Tue 23/04/02 Wed 24/04/02 8 hrs
Review functional specifications
Wed 15/05/02 Fri 17/05/02 16 hrs
Incorporate feedback into functional specifications
Fri 17/05/02 Mon 20/05/02 8 hrs
Obtain approval to proceed
Mon 20/05/02 Mon 20/05/02 4 hrs
Project Manager
Tue 02/04/02 Fri 23/08/02 104 hrs
Define preliminary resources
Tue 02/04/02 Tue 02/04/02 8 hrs
Secure initial resources
Wed 03/04/02 Thu 04/04/02 16 hrs
Confirm preliminary budget
Wed 17/04/02 Thu 18/04/02 16 hrs
Review software specifications/budget with team
Fri 19/04/02 Fri 19/04/02 4 hrs
Develop delivery timeline
Mon 22/04/02 Tue 23/04/02 8 hrs
Obtain approvals to proceed (concept, timeline, budget)
Tue 23/04/02 Wed 24/04/02 8 hrs
Secure required resources
Wed 24/04/02 Thu 25/04/02 8 hrs
Obtain approval to proceed
Mon 20/05/02 Mon 20/05/02 4 hrs
Identify test group
Thu 25/04/02 Fri 26/04/02 8 hrs
Document lessons learned
Tue 20/08/02 Wed 21/08/02 8 hrs
Distribute to team members
Wed 21/08/02 Thu 22/08/02 8 hrs
Create software maintenance team
Thu 22/08/02 Fri 23/08/02 8 hrs
Creative Director
NA NA 0 hrs
Analyst
Tue 09/04/02 Wed 15/05/02 172 hrs
Draft preliminary software specifications
Tue 09/04/02 Tue 16/04/02 48 hrs
Review software specifications/budget with team
Fri 19/04/02 Fri 19/04/02 4 hrs
Incorporate feedback on software specifications
Fri 19/04/02 Mon 22/04/02 8 hrs
Review preliminary software specifications & graphical design
Thu 25/04/02 Tue 30/04/02 24 hrs
Develop functional specifications
Tue 30/04/02 Thu 09/05/02 56 hrs
Develop prototype based on functional specifications
Thu 09/05/02 Wed 15/05/02 32 hrs
Developer
Tue 21/05/02 Thu 11/07/02 424 hrs
Review functional specifications
Tue 21/05/02 Tue 21/05/02 8 hrs
Identify modular/tiered design parameters
Wed 22/05/02 Wed 22/05/02 8 hrs
Assign development staff
Thu 23/05/02 Thu 23/05/02 8 hrs
Develop code
Fri 24/05/02 Thu 11/07/02 280 hrs
Developer testing (primary debugging)
Wed 05/06/02 Wed 26/06/02 120 hrs
Testers
Tue 21/05/02 Fri 02/08/02 280 hrs
Develop unit test plans using product specifications
Tue 21/05/02 Fri 24/05/02 32 hrs
Develop integration test plans using product specifications
Tue 21/05/02 Fri 24/05/02 32 hrs
Review modular code
Wed 26/06/02 Wed 03/07/02 40 hrs
Test component modules to product specifications
Wed 03/07/02 Fri 05/07/02 16 hrs
Identify anomalies to product specifications
Fri 05/07/02 Wed 10/07/02 24 hrs
Modify code
Wed 10/07/02 Mon 15/07/02 24 hrs
Re-test modified code
Mon 15/07/02 Wed 17/07/02 16 hrs
Test module integration
Wed 17/07/02 Wed 24/07/02 40 hrs
Identify anomalies to specifications
Wed 24/07/02 Fri 26/07/02 16 hrs
Modify code
Fri 26/07/02 Wed 31/07/02 24 hrs
Re-test modified code
Wed 31/07/02 Fri 02/08/02 16 hrs
Trainers
Tue 21/05/02 Tue 30/07/02 256 hrs
Develop training specifications for end users
Tue 21/05/02 Thu 23/05/02 24 hrs
Develop training specifications for helpdesk support staff
Tue 21/05/02 Thu 23/05/02 24 hrs
Identify training delivery methodology (computer based training, classroom, etc.)
Tue 21/05/02 Wed 22/05/02 16 hrs
Develop training materials
Wed 26/06/02 Wed 17/07/02 120 hrs
Conduct training usability study
Wed 17/07/02 Tue 23/07/02 32 hrs
Finalize training materials
Tue 23/07/02 Fri 26/07/02 24 hrs
Develop training delivery mechanism
Fri 26/07/02 Tue 30/07/02 16 hrs
Technical Communicators
Tue 21/05/02 Tue 16/07/02 336 hrs
Develop Help specification
Tue 21/05/02 Tue 21/05/02 8 hrs
Develop Help system
Tue 18/06/02 Tue 09/07/02 120 hrs
Review Help documentation
Tue 09/07/02 Fri 12/07/02 24 hrs
Incorporate Help documentation feedback
Fri 12/07/02 Tue 16/07/02 16 hrs
Develop user manuals specifications
Tue 21/05/02 Wed 22/05/02 16 hrs
Develop user manuals
Tue 18/06/02 Tue 09/07/02 120 hrs
Review all user documentation
Tue 09/07/02 Thu 11/07/02 16 hrs
Incorporate user documentation feedback
Thu 11/07/02 Mon 15/07/02 16 hrs
Deployment Team
Fri 02/08/02 Tue 20/08/02 96 hrs
Install/deploy software
Fri 02/08/02 Mon 05/08/02 8 hrs
Obtain user feedback
Mon 05/08/02 Mon 12/08/02 40 hrs
Evaluate testing information
Mon 12/08/02 Tue 13/08/02 8 hrs
Determine final deployment strategy
Tue 13/08/02 Wed 14/08/02 8 hrs
Develop deployment methodology
Wed 14/08/02 Thu 15/08/02 8 hrs
Secure deployment resources
Thu 15/08/02 Fri 16/08/02 8 hrs
Train support staff
Fri 16/08/02 Mon 19/08/02 8 hrs
Deploy software
Mon 19/08/02 Tue 20/08/02 8 hrs
The Customer
Mon 18/03/02 Fri 29/03/02 0 hrs
Decision on preferred bidders
Mon 18/03/02 Mon 18/03/02 0 hrs
Award contract
Fri 29/03/02 Fri 29/03/02 0 hrs